Construction Alerts

Academic Instructional Center elevator repair

August 05, 2026 - February 5, 2027

Materials needed for repairing the central elevator in the Academic Instructional Center are expected to arrive near the end of December during the holidays. The contractor has cleared the schedule for the repair crew beginning the second week of January, with completion expected in early February. The east elevator remains in service.

Communications Facility Data Center

July 01, 2026 - June 15, 2027

The Data Center Relocation project will move WWU's data center from the Academic Center to Communications Facility on the main campus. The relocation will provide more robust telecom infrastructure for campus and an emergency generator to back up all systems reducing future interruptions. Work will continue through summer of 2027.

Wilson Library main entrance

June 24, 2026 - December 15, 2026

Primary construction to add an accessible ramp to the main entrance on the north side of Wilson Library is complete, and the handrails on the stairs are being installed. Guardrails for the ramp are expected in December. 

Western Welcome Center

March 24, 2026 - September 30, 2027

Construction for the Western Welcome Center, located at the south end of the academic core of campus, began March 24, 2026. Completion is expected in fall of 2027. The construction zone includes Flag Plaza and parking lot 19G, both of which will remain closed for the duration of construction. Please see the construction impact page for more details and updates.