Project Close-out
- Change e-Builder status to “Close-out”
- O&M manuals and equipment
- Substantial completion
- Physical Close-out
- Final completion
- Internal Close-outs
- Electronic and paper document archiving
- Update e-Builder status to “complete”
- Celebrate!
Internal Close-outs
Final certificate triggers Capital Budget Office close-out process in e-Builder.
Capital Budget prepares lien notice advertisement and submits for publication.
Date of project completion is the date the Director signs the Final Completion certificate.
Send memo to Lockshop to pull keys except one-year warranty set.
Close AiM assist:
- Review phases.
- Work with supervisors to complete and close.